The Restaurant Pre-Opening: 90 Days Before Opening
By Ray Camillo /
A restaurant pre-opening plan covers the last 90 days before you open the doors. In those 90 days you hire the team, train them, stock the fridge and dry storage, and test the operation. How well that work goes affects your reviews, your staff turnover, and your cash in the first year.
Most owners spend this time watching construction. Schedule the operating work in the same detail.
This post assumes you have a signed lease, a funded budget, and construction underway. Count backward from the date you plan to open.
Days 90 to 61: Hire Your Managers and Finalize the Menu
Begin your restaurant pre-opening plan with two hires: the general manager and the chef. Put them on payroll about 90 days out. They write the recipes, procedures, and training the hourly staff will use.
Start that search early. The National Restaurant Association’s 2026 outlook found nearly three quarters of operators plan to hire. Those same operators expect trouble finding experienced managers and chefs.
Teach “Management School.” Your management team is new. New to the business, new to each other. They do not yet know how to work together as a team, let alone unite to deliver your new brand. Carefully selecting each manager for talent and experience doesn’t change that. Management School should align the team behind your guiding principles, the promises you are making to your staff about work environment and culture, the promises you are making to your guests, and the promises you are making to stakeholders. Don’t leave it to chance.
Finalize the menu during this period. A final menu has every recipe written, tested, and costed, with a plating photo. The kitchen can’t order, prep, or train from a menu that keeps changing.
Apply for the liquor license if you haven’t. Approval takes weeks in some states and months in others. Ask your local licensing office how long approvals are running, then add time to that.
Choose the point-of-sale system, payroll provider, and reservation platform now. Each one takes weeks to set up. Someone also has to program the menu into the POS before training starts.
Days 60 to 31: Recruit Hourly Staff and Write the Training
Post hourly jobs about 60 days out and interview around day 45. Restaurant Business reported that 47 percent of operators have job openings that are hard to fill. Hire more people than the schedule needs, because some new hires quit during training…and some turn out to be a poor fit.

Write the training manuals before the staff arrives. Each position needs a daily training schedule and a written test. Pick your trainers now and teach them how to train. A Train-the-Trainer class keeps five trainers from teaching five different ways.
Order smallwares, uniforms, printed menus, and opening inventory. Set up vendor accounts and credit terms. Check delivery dates against the construction schedule. China delivered to an unfinished building gets broken or lost.
Schedule the health, fire, and building inspections with your contractor. Ask each inspector what they need to see. A failed inspection can push the opening back a week or more.
Days 30 to 8: Train the Staff in the Building
Bring hourly staff in two to three weeks before opening. Cooks make every menu item several times. Servers taste every dish, learn the POS, and practice the steps of service.
Budget for training payroll. Servers earn no tips in training, so you pay them at least full minimum wage. Here’s a rough example for a full-service restaurant.
• 45 hourly employees.
• 50 hours of training each.
• An average training wage of $15 an hour.
That’s $33,750 in wages before payroll taxes, with no sales to offset it. Add the cost of the food you use for training and tastings.
Test the equipment and systems during these weeks. Run every burner, the dish machine, and the walk-in for full days. Send a test ticket from each POS terminal to each kitchen printer. Run a test credit card. Repair what fails while the contractor is still on site.
The Last Week: Mock Service and a Soft Opening
Run at least two mock services before any guest pays. Half the staff sit as guests while the other half works, and then they switch.
Follow with a friends-and-family night. Invite enough people to fill half the dining room. Seat tables 15 minutes apart so the kitchen never gets more than a few tickets at once.
After each practice service, meet with the managers and list what went wrong. Pick the three biggest problems and solve them before the next service.
Then open without an announcement. In a soft opening, you unlock the doors and serve whoever comes in. Shorten the hours or the menu for the first week if the staff needs it.
Wait Two or Three Weeks for the Grand Opening
Schedule press, influencers, and the grand opening two to three weeks after the soft opening. On day one, the staff is working its first real shift. Guests who wait 40 minutes for food that night write your first reviews.
Start with the neighbors. Invite nearby businesses, the landlord, and residents to the friends-and-family night. They’re the guests most likely to become regulars.
Budget for the Restaurant Pre-Opening Plan and the Months After
Give your restaurant pre-opening plan its own budget. Include manager salaries, training payroll, training food, opening inventory, uniforms, and marketing.
Then set aside operating cash for after you open. Sales in the first months usually don’t cover costs. Our post on surviving year one explains the ramp-up period and how much reserve to keep.
Expect delays. Equipment arrives late, an inspection gets rescheduled, or the liquor license takes longer than quoted. If the opening date moves after you’ve hired staff, you keep paying them or you lose them. Don’t set hourly start dates until the final inspections are on the calendar.
Use the Restaurant Pre-Opening Plan in the First 30 Days
Keep your trainers working shifts for the first two weeks of service. Check ticket times, comps, and voids every day. Retest staff on the menu at day 14. Compare actual labor and food cost to the budget at day 30.
Put the restaurant pre-opening plan in writing. Give every task a date and one person responsible for it.
Planning an opening in the next year? Book an introductory call or schedule an advisory session.